The
Supreme Court on Friday ruled that Indian Railways cannot claim the status of a
“deemed distribution licensee” under the Electricity Act, 2003, holding that it
functions as a “consumer” of electricity and is therefore liable to pay
cross-subsidy surcharge (CSS) and additional surcharge (AS) to distribution
companies.
A
Bench of Justice Dipankar Datta and Justice Satish Chandra Sharma said the
Railways’ electricity infrastructure is meant exclusively for its own
operational needs, including traction systems, signalling and station-related
services, and does not involve supply of electricity to outside consumers.
“The
erection of transmission lines or distribution lines, as argued by the
appellant (Railways), cannot bestow upon the appellant the authorisation to
carry out supply of electricity that is procured by it, to third-party
consumers... It is only when electricity is sold or provided to consumers
outside the operational domain of the Railways that the activities undertaken
by the appellant could intersect with the obligation of a distribution
licensee,” the Bench observed.
The
Court further said that Railways purchases electricity only for
self-consumption and supplies it solely within its own network.
“The
appellant is a consumer within the meaning and scope of Section 2(15) of the
Electricity Act. It purchases electricity exclusively for its own use and
supplies it to no one but its own constituents. Thus, like any other consumer,
cross-subsidy surcharge and additional surcharge are applicable to the
appellant,” the judgment added.
The dispute centred on Railways’
contention that it qualified as a deemed distribution licensee under the third
proviso to Section 14 of the Electricity Act.
It had argued that its extensive
electricity network for railway operations constituted a “distribution system”,
entitling it to procure power through open access without paying cross-subsidy
surcharge and additional surcharge.
The issue dates back to 2015,
when Indian Railways sought connectivity for procurement of 100 MW electricity
through inter-state open access for traction substations. Following objections
over its legal status, the matter reached the Central Electricity Regulatory
Commission (CERC), which ruled in favour of Railways and recognised it as a
deemed distribution licensee.
That finding was subsequently
overturned by the Appellate Tribunal for Electricity (APTEL), which held that
Railways was not engaged in distribution of electricity in the manner
contemplated under the Electricity Act. Railways then challenged the APTEL
ruling before the Supreme Court.
In the judgment authored by
Justice Sharma, the Court held that an entity can qualify as a deemed
distribution licensee only if it satisfies two conditions under Section 14 of
the Act: operating and maintaining a distribution system for supply of
electricity to consumers, and supplying electricity within a defined area of
supply.
According to the Court, Railways
failed to meet these requirements because its electricity network exists solely
for internal consumption and does not involve supply to independent consumers
within any designated area of supply.
The Bench also flagged the
financial implications of exempting high-volume consumers such as Railways from
payment of surcharges.
“When high-volume, high-revenue
consumers such as the Indian Railways choose to procure electricity through
open access, distribution licensees may be left with underutilised
infrastructure and power purchase commitments, leading to financial strain,”
the Court observed.
It added that “the cross-subsidy
surcharge and the additional surcharge are critical for maintaining the
financial health and operational capacity of the distribution sector, enabling
it to invest in infrastructure upgrades, ensure reliable service, and continue
to meet its obligations to all consumer categories”.
Dismissing the appeal, the Court
directed the respondent distribution companies to calculate and issue detailed
statements of outstanding cross-subsidy surcharge and additional surcharge
payable by Railways, segregated according to the relevant area of supply and
period of open-access procurement.
The Bench said Railways would be
given time to respond to the claims, subject to scrutiny by the appropriate
electricity regulatory commission.
Ramanuj Kumar, partner at law firm Cyril Amarchand Mangaldas, said the
judgment is likely to have a significant impact on Indian Railways’ existing
and planned bilateral power procurement, as imposition of CSS and AS on such
procurement will result in a steep increase in Railways’ landed power
procurement cost under such power purchase agreements (PPAs), including from
renewable power projects, potentially rendering such procurement significantly
less attractive.